Meridian Te Apiti Wind Farm Project Jan - Sept 2004

55 Windmills total made up components as follows:

55 Inground bases = 22.5 loads each base 4.5m dia 11 ton each. 27 ton of reinforcing and 373 cube of concrete to hold them in the ground. 

Out of ground: 55 Bottom sections = 55 loads 4.5m dia 17 meters long. 3 days to weld inside and out bottom section to base. 

55 Mid sections = 55 loads 4.2m dia 19 meters long Bolted together 55 top sections = 55 loads 3.1m dia 31 meters long. Bolted together. 

All loads averaged a combined weight inclusive of transporter of 110 ton approx. Empty transporter average weight 60 - 70 ton. 

55 Nacelles (turbines) = 55 loads 3.1m wide 50.4 ton each. 

Once the towers started moving to site they where in uniform Bottom / Mid / Top and turbine. These had to be erected all on the same day with the turbine placed on top for stability. 

55 Hubs = 55 loads 3.1m dia 21 ton each. 

165 Blades = 82.5 loads each blade 6 ton and 35 meters long carried off set vice / versa with a total length of just on 50 meters including transporter.

 

Dependant on the time of departure and item travel times were between 3.5 - 6 hours per trip. All Tower and Turbine loads were towed up the Saddle Rd from the bottom to each site.

TRANZCARR Heavy Haulage Ltd

134 Plunket Avenue, Manukau, Auckland, New Zealand

PO Box 23194, Hunters Corner, Manukau 2155, New Zealand